Project to build a structural steel arch at km 19.8 from LA1 road to Laforge dam 1

Information on the project

Proponent

James Bay Development Corporation

Administrator

Provincial administrator

Reference number

3214-05-085

Subscribe to the email alerts for this project

Do you need more information ?

Contact-us by e-mail at [email protected]

Summary

Due to an exceptional flood in the late spring of 2018, the battery of six culverts under the road at km  19.8 gave way causing the road to subside. The planned works consist mainly of:

1. Moving the temporary bridge that was built in an emergency. It must be moved to allow the construction of the permanent structure in the axis of the current road. The temporary bridge will then remain in place during the construction of the permanent arch.

2. Construction of the permanent structural steel arch made of steel over the watercourse.

3. Dismantling of the temporary bridge.


Documents

Preliminary information

Table provided by MDDELCC

Additional information



Disclaimer

Some of the information on this website may have been supplied by external sources. The Evaluating Committee assumes no responsibility for the accuracy, timeliness or reliability of information supplied by external sources. Users wishing to rely on this information should consult directly with the appropriate source.